(TOWN OF KIRKWOOD, NY) – The Broome County Department of Public Works has the final construction timeline for the rehabilitation of three county-owned bridges along County Route 20 in the Town of Kirkwood.
The three bridges to be rehabilitated are:
- CR 20 over Susquehanna River/ Norfolk Southern Railroad (BIN 3349250)
- CR 20 over NYS&W Railroad (BIN 3349370)
- CR 20 over Main Street (Kirkwood) (BIN 3349360)
Construction is scheduled to begin on April 1, 2026, and to be completed in the fall of 2026. Single-lane closures will occur intermittently from April 1 through June 1, 2026, and after September 1, 2026, until construction is completed.
The bridges will be completely closed to traffic from June 1 through September 1, 2026, with detours in place during that time.
Businesses, schools, and municipalities are encouraged to plan accordingly.